• The years 2008-2010 have lead to the company's development and increased the number of employees.
  • The years 2011-2012 were marked by the successful finalizing of four projects: Budac I and Budac II HPD, on the Budac river, Bistrița-IstorieNăsăud county, total installed power of 2,7MW; Cugir HPD on the Cugir river, Alba county, total installed power of 2,09MW and Boșorog HPD, on the Boșorog river, Alba county, total installed power of 1,49MW.
  • In 2012, 4C PROJECT CONSULTING has supplemented the activity with due diligence section.
  • Between the years 2013-2015 were put into service the following projects: Răcătău HPD, Cluj county, total installed power of 1,367MW, Bistra HPD, Alba county, total installed power of 936 kW, Drăgan I and Drăgan II HPD, Bihor county, total installed power of 3.948 MW, Budușel HPD, Bistrița-Năsăud county, total installed power of 891 kW and Nirajul Mare HPD, Mureș county, total installed power of 1,646 MW.
  • In the first part of 2015,  Budac I HPD and Bolovanu HPD have been refurbished and rehabilitated, having  a total installed power of 0.616 MW, respectively 0.91 MW, both located in Bistrita county.
  • Regarding services, since 2015, the company has completed work with monitoring and reporting of energy production services.
  • Regarding design work, since 2015, the company designs piscicultural works of water supply and sanitation networks.